2023 OM 2

1234567891011121314
Across
  1. 3. when limited capacity of process causes work to pile up
  2. 5. Average time for item to move thru system
  3. 7. Fixed timing of item movement thru process
  4. 8. Time between two consecutive parts completion
  5. 9. symbol is rectangle
  6. 11. Time activated divided by time available is --
  7. 12. inventory kept to ensure continuation of subsequent operation
  8. 14. Operation must stop as there is no place to store completed item
Down
  1. 1. symbol is diamond
  2. 2. Throughput time divided by value-added time is ---
  3. 4. symbol is triangle
  4. 6. Sum of setup and tun time = --- time
  5. 10. Operation must stop since there is no work
  6. 13. symbol is arrow