BASIC WORK EXECUTION
Across
- 3. Meaning of BM
- 6. The culmination of engineering and procurement activities.
- 8. On this phase, the designs for equipment are finalized before we proceed with our issuance of purchase order to vendors
- 11. It marks vendor’s start of fabrication.
- 12. The functionality of the equipment is checked at the factory.
- 14. This is a critical alignment window where Engineering secures Technical Confirmation and reviews the master schedule, while Procurement locks in Commercial Confirmation.
- 15. It is the second most important contractual document to purchase the package units.
Down
- 1. Meaning of BQ
- 2. It is a summary of technical evaluation results in the form of the tabulated requirements and bidder proposed data.
- 4. Which department issues the copy
- 5. On this phase, the pre-qualification, evaluation and selection of potential suppliers (Vendors) are carried out.
- 7. The document that specifies the full detail of the equipment process and mechanical design conditions and operating performance, etc.
- 9. Which department issues the foundation drawing and paving plan drawing?
- 10. Which department issues the control architecture and cabling requirements of the project?
- 13. To which department does Mechanical relay the schedule, issues, and concerns, as well as the progress report?