G033-1

12345678910111213141516171819202122232425262728293031323334
Across
  1. 2. When selecting cables, the 3 main requirements are CCC, VD and ______.
  2. 4. To decrease time spent fault finding, use the ______ split method.
  3. 5. The first and last thing you should when isolating a circuit before working on it, is _____ the meter.
  4. 7. _______ error can cause a false reading on older analogue meters.
  5. 10. When looking at a standard 230 volt socket outlet, the earth is on the bottom and the _______ socket is on the right.
  6. 11. AS3000 Cl. 1.4.9 is about appliances, which do not include _______.
  7. 12. AS/NZS 3008.1 is the cable _________ standard.
  8. 14. The safest way to test an installation is to have the _______ off.
  9. 15. IZ = current carrying capacity of the cable, and must not be _______ than the current in the circuit.
  10. 17. A _______ core/conductor is not included in the cable supplying a star or delta connected 3 phase motor.
  11. 19. Table ______ point two can be used for resistance values of protective earthing conductors (Re), but in any case the resistance must be low enough to ensure the cb trips during a fault.
  12. 21. Before isolating power and applying your tag/padlock, you should test if the ___________ is at the appliance. This way, you can be more certain the you are isolating the correct circuit.
  13. 24. 11.5 volts is ______ % of 230 volts.
  14. 26. How many 10amp double socket outlets can we install on a 20amp cb in a non-domestic situation.
  15. 27. 218.5 volts is the _________ voltage that can measured at a 230 volt socket outlet to comply with voltage drop requirements.
  16. 28. A certificate of __________ must be issued to the customer for all electrical work, and the contractor must also keep documentation.
  17. 32. The insulation of final subcircuits need not be tested between active and neutral (to avoid damage to electronics) but must be tested between both A/N and ________.
  18. 33. A coil inside a motor is touching the metal frame. This would be known as a ________ circuit fault.
  19. 34. The approximately 7 times the rated current that flows into a motor during starting is sometimes called ________ current.
Down
  1. 1. Most loads are wired in __________ so that they receive the same voltage.
  2. 3. Testing is a requirement under electrical legislation, but what we are trying to accomplish is to find ________.
  3. 6. Which type of circuit would all loads be off if one of the loads became open circuit?
  4. 8. The voltage read across a closed light switch, while the circuit is energised, should be near _______.
  5. 9. When designing an installation the ________ short circuit current available at the supply needs to be considered.
  6. 12. Table C9 helps us determine the number of circuits in our switchboard by giving guidance on the number of points we can connect to a final _____________.
  7. 13. _____ < or = IN < or = IZ
  8. 16. __________ are connected in series with loads.
  9. 18. The "L" terminal on a light switch is the ________ terminal and is not switched.
  10. 20. Hot joints in switchboards, even before they cause insulation breakdown, can be detected with a _______ imaging camera.
  11. 22. If you read 230 volts across the switch of a light circuit, the switch is _______.
  12. 23. The two parts considered during design are the supply and the customers installation (which meet at the point of supply). When considering the installation side, an important consideration is the ________ arrangement.
  13. 25. Don't connect the laundry and kitchen socket outlets on the same circuit to avoid _________ the cb.
  14. 29. Equipotential bonds and the ______ earth must not have a resistance greater than 0.5 ohms.
  15. 30. The neutral of any final subcircuit must ____ be connected to any other final subcircuit neutral (other than at the neutral bar).
  16. 31. IN < IZ is known as ___________ between cables and circuit breakers (refer to cl 3.4.4).