Across
- 4. Estimate of the......time that an activity would take is called the most likely time.
- 7. An activity is called critical If......float is zero.
- 8. Forward pass calculation is used to find.......time.
- 9. The longest path in a network diagram is called.......path.
- 10. Critical path method is a.........Method.
- 13. What is short name of Critical Path Method?
- 14. If everything goes on well then the optimistic time is the.......possible time to complete the activity.
- 15. What is short name of project evaluation and review technique?
Down
- 1. In.....models there are risk and uncertainty.
- 2. Backward pass calculation is used to find........time.
- 3. How many phases are involved in project management?
- 5. Probabilistic models are also known as........Models
- 6. If everything goes wrong, then the longest time that an activity would take is called......time.
- 11. The difference between total float and free float is known as......float.
- 12. Negative Independent float always taken as......