Across
- 3. a method that used for developing schedule by compressing the project duration and may add extra cost
- 4. a sign for project completion but has no duration
- 6. government release the newest effective working hour that may impact to the project duration due to covid 19 is the good example of
- 8. defining the procedure about how to process all the activities in the project schedule management
- 11. amount of time an activity can be delayed without delaying the project end date
- 12. use mathematical relationship to define activity duration
- 13. breaking down the work package into activities
- 14. one of the estimating activity duration that used similar schedule in the last project
- 16. you use 3 different time to estimate activity duration
- 17. critical activities must have... total float
Down
- 1. you boss try to fasten the activity duration by using multitasking system called...
- 2. one of the techniques use to estimate activity duration
- 5. you use previous project lesson learned to define the activities is the good example of
- 7. the number of workdays to complete the task
- 9. connecting between on activity to another activity
- 10. one of the technique to define activities in the project
- 13. the number of workdays plus elapsed time
- 15. there are two activities that should be completed but they have a chance of producing reworks, you try to add some times to make a lil bit loose so if the reworks happen, they are still have time to fix it.