Scheduling Vocabulary

12345678910111213141516171819202122232425
Across
  1. 2. Required to complete an activity.
  2. 5. Most probable schedule.
  3. 6. activity which succeeds another one.
  4. 10. ____schedule; aggressive with no reserve.
  5. 11. The way an activity is related to every other one.
  6. 17. Activity which precedes another
  7. 19. Limitation applied to the start or completion of an activity
  8. 20. _____engineering; design, drafting, and specialists
  9. 21. Logic ____, relationship between predecessor and successor activities
  10. 23. Construction ____, time from EFS to mechanical completion.
  11. 24. Point where 50% of work hours are expended
  12. 25. Calculated schedule contingency.
Down
  1. 1. Summary activity
  2. 3. ____ engineering start, contract award for engineering.
  3. 4. Abbreviation; breaks the project into manageable elements.
  4. 5. ___centroid; 50% of materials are committed.
  5. 7. Special cost and allowance
  6. 8. best estimate of how long an activity will take.
  7. 9. _____span, time from EES to 95% complete.
  8. 12. The longest path,measured in time, that can be trace through a schedule which has zero float
  9. 13. ____construction labor; work hours associated with installing the physical facility
  10. 14. Abbreviation: Critical path method
  11. 15. ____completion; 100% complete and facility can be operated.
  12. 16. Logic ____, a graphic depiction of a project.
  13. 18. When a major accomplishment is achieved.
  14. 19. ____activities that are located in the critical path.
  15. 22. Total ____; amount of time an activity can be delayed without affecting completion date.